Onshore Pipeline Project, Australia
Delivering coated pipes for a major Australian pipeline project required more than transport: it demanded precision. Trans Global Projects combined multimodal shipping with advanced handling and QA processes to ensure every pipe and bend arrived safely and met strict technical standards.
FACTS & FIGURES
Client
A major international steel pipe contractor
Location
Mundra, India to Kurri Kurri, NSW, Australia
Project Period
2023 – 2023
Total Cargo Weight / Volume
36,000 cbm
SCOPE OF WORK
Cargo consisted of DLFBE coated pipe 42″ OD, 14″OD and bends. Cargo was shipped from Mundra, India to Newcastle, Australia, stored and then delivered to Kurri Kurri in NSW, Australia.
TGP provided online data reporting, custody transfer, QA testing with holiday detection equipment, all machinery for cargo handling including vacuum technology fitted to excavators.