Multiple Power Transformer Delivery Programme, USA

Trans Global Projects managed the door-to-door transport of 47 power transformers from Brazil to the USA, overseeing engineering calculations, barge loadouts and full project coordination across multiple phases of ocean and inland transport.

FACTS & FIGURES

Client
An international power equipment manufacturer

Location
Brazil to USA

Project Period
2024 – 2025

Total Cargo Weight / Volume
6,195 mt / 10,048 cbm
Various weights ranging from 58 mt to 206 mt (ongoing).

SCOPE OF WORK

TGP was involved in transporting multiple transformers of varying weights from Brazil to USA. 11 x transformers delivered in 2024. 36 x transformers delivered in 2025.

Scope of work involved door to door transport, including engineering calculation, loadout to barge and overall project management. Multiple transformers ranging from 58 mt to 206 mt, from Brazil to USA.