HDPE and PP Plant & HAOR Modernisation

Trans Global Projects managed the delivery and modernization of HDPE and PP plants, as well as the HAOR facility in Azerbaijan, coordinating multimodal transport of oversized cargo from global origins via land, sea and river routes to Sumgait and Baku.

FACTS & FIGURES

Timeframe
Project duration: 2016–2018 & 2018–2021. Transport and delivery to site completed.

Route
Shipments originated from Italy/Europe, India, Korea and China. Routes included the Black Sea and Russian river system, with final delivery to Sumgait and Baku, Azerbaijan.

Client
A leading EPC contractor in the oil & gas sector with global reach.

Transport
Multimodal transport via land, sea and inland waterways.

The Cargo
Approx. 70,000 cbm of cargo.

Key items included
• 11 pressure vessels, largest: 346 mt / 56.25 x 7.00 x 8.85 m
• DHT reactor: 527 mt / 32.65 x 8.40 x 6.61 m

SYNOPSIS

TGP managed the delivery and modernisation of HDPE and PP plants, as well as the HAOR facility in Azerbaijan. Cargo was shipped from global origins via land, sea and river routes to Azerbaijan.

Download Case Study (PDF)